Variscan’s Resource Surge Raises Questions on Mine Restart Viability and Next Steps
Variscan Mines has announced a transformative update to its Novales-Udías Project, tripling its zinc-lead Mineral Resource Estimate and raising over $2 million to advance development. Drilling is underway with a Mine Re-Start Study on track for mid-2025.
- Updated JORC Mineral Resource Estimate triples to 3.4Mt at 7.6% Zn and 0.9% Pb
- Measured Resources defined for the first time, enhancing geological confidence
- Drilling commenced at Udías Mine with assay results expected soon
- Fully underwritten renounceable entitlement offer raised $2.07 million
- Mine Re-Start Study for San Jose Mine scheduled for H1 2025
A Major Leap in Resource Confidence
Variscan Mines Limited (ASX:VAR) has delivered a landmark update for its Novales-Udías zinc-lead project in northern Spain, announcing a tripling of its Mineral Resource Estimate (MRE) to 3.4 million tonnes at an impressive 7.6% zinc and 0.9% lead grade. This substantial increase, detailed in the December 2024 quarterly report, marks a significant milestone in the company’s exploration and development trajectory.
For the first time, the MRE includes Measured Resources, reflecting a higher degree of geological confidence and underpinning the robustness of the project’s resource base. The upgraded estimate positions Novales-Udías as one of the highest-grade zinc deposits held by an ASX-listed company, a notable achievement in the competitive zinc exploration sector.
Drilling Progress and Exploration Upside
Drilling activities commenced in mid-November 2024, focusing on priority targets identified through historic underground sampling and recent assays that confirmed mineralisation beyond the existing resource footprint. The current drilling campaign is concentrated at the Udías Mine, a complex several times larger than the San Jose Mine and previously untested by Variscan’s drilling efforts.
Importantly, mineralisation remains open both along strike and at depth, with over 60% of the 12-kilometre Novales trend yet to be incorporated into the MRE. This suggests considerable upside potential as further drilling results are expected shortly, with a subsequent resource update anticipated in 2025.
Financial Strength and Development Pathway
Supporting these exploration advances, Variscan successfully completed a fully underwritten renounceable entitlement offer in October 2024, raising approximately $2.07 million before costs. This capital injection strengthens the company’s balance sheet, enabling sustained development activities and the advancement of a Mine Re-Start Study focused on the San Jose Mine.
The study, scheduled for delivery in the first half of 2025, will leverage the upgraded MRE, particularly the Measured and Indicated Resources totaling 1.7 million tonnes at 8.6% zinc and 1.4% lead. San Jose Mine, with existing mining licenses and infrastructure, is earmarked as the initial production hub, with potential operational integration with the adjacent Udías Mine complex.
Strategic Outlook and Next Steps
Variscan’s Managing Director Stewart Dickson highlighted the transformational nature of the quarter, emphasizing the tripling of the resource inventory and the commencement of drilling at Udías as key catalysts. The company is poised to unlock further value through ongoing assay results, metallurgical test work, and the upcoming Mine Re-Start Study.
With exploration expenditure of $527,000 during the quarter focused on underground drilling, geological modelling, and technical consulting, Variscan is methodically advancing its Spanish zinc assets within a region boasting established mining infrastructure. The company’s strategic approach balances resource expansion with financial prudence, as evidenced by the recent capital raise and disciplined cash management.
Bottom Line?
Variscan Mines’ resource expansion and funding success set the stage for a pivotal 2025 as drilling results and the Mine Re-Start Study promise to define the project’s commercial viability.
Questions in the middle?
- How will upcoming assay results from Udías Mine influence the next resource update?
- What are the key economic assumptions underpinning the Mine Re-Start Study for San Jose Mine?
- Could operational integration of San Jose and Udías Mines enhance project economics?