Kiniero Project Mines 82,000+ Tonnes, On Track for Q4 2025 Gold Pour

Robex Resources has commenced mining at its Kiniero Gold Project in Guinea, maintaining its schedule and budget to achieve first gold production by the fourth quarter of 2025.

  • Mining operations underway with ore delivered to ROM pad
  • Construction of process plant and tailings facility progressing on schedule
  • Grade control drilling confirms robustness of mineral reserve model
  • Power station and major plant components nearing completion
  • Project remains LTI free with strong safety record
An image related to ROBEX RESOURCES INC.
Image source middle. ©

Mining Commences at Kiniero

Robex Resources Inc. has officially begun mining activities at its Kiniero Gold Project in Guinea, marking a significant milestone as the company advances towards its goal of first gold production in the fourth quarter of 2025. The project remains on track and within budget, reflecting steady progress across multiple fronts.

Construction and Development Progress

Key infrastructure developments are well underway. The process plant assembly is nearing completion, with major components such as the SAG and Ball Mills almost fully installed. The tailings storage facility is advancing steadily, with embankment construction and lining progressing as planned. Meanwhile, the power station is 45% electrically complete, with four 4 MW engines delivered and installation scheduled to begin imminently.

Operational Readiness and Safety

Mining operations have commenced on both day and night shifts, with over 82,000 tonnes of material mined, including more than 20,000 tonnes of ore delivered to the Run-of-Mine pad. The project boasts an impressive safety record, having completed nearly 4.9 million hours without a lost time injury. Grade control drilling continues to validate the mineral reserve model, supporting confident short-term mine planning.

Looking Ahead

Robex is mobilizing its operations readiness and commissioning teams, with commissioning activities set to begin next month. The company plans to complete the installation of critical equipment, including the four engines at the power station, and ramp up mining activities to full production. These steps are crucial as the project moves from construction to operational phases.

Context and Risks

While the project is progressing well, Robex acknowledges the inherent risks associated with mining operations in West Africa, including geopolitical uncertainties and financing challenges. The company’s forward-looking statements highlight these risks alongside assumptions about gold prices, operational execution, and regulatory compliance.

Bottom Line?

With mining underway and commissioning imminent, Robex is poised to deliver on its promise of gold production in late 2025, but investors should watch closely for operational and geopolitical developments.

Questions in the middle?

  • Will Robex maintain its safety record as production scales up?
  • How will geopolitical conditions in Guinea impact ongoing operations?
  • What are the financing plans to support ramp-up beyond initial production?