Lotus Resources has achieved a key milestone at its Kayelekera Uranium Mine with the first high-grade ore delivered to the ROM pad, setting the stage for steady-state production targeted in early 2026. The company has also secured multiple sulphuric acid suppliers and is on track to commission its acid plant to ease supply constraints and reduce costs.
Maxwell Dee
Maxwell Dee
23 Dec 2025
Lotus Resources plans a significant share consolidation to better align its capital structure with its ASX300 status, aiming to attract a broader investor base. The move, subject to shareholder approval, coincides with a proposed update to the company’s constitution.
Maxwell Dee
Maxwell Dee
10 Dec 2025
Lotus Resources reports promising progress at its Kayelekera uranium mine, targeting steady state production by Q1 2026 despite recent sulphuric acid supply constraints. The company is addressing supply issues with new sourcing and an on-schedule acid plant rebuild.
Maxwell Dee
Maxwell Dee
4 Dec 2025
Lotus Resources has marked a major milestone with first yellowcake production at its Kayelekera uranium mine in Malawi, progressing steadily towards full production in early 2026 while advancing its Letlhakane project in Botswana.
Maxwell Dee
Maxwell Dee
30 Oct 2025
Lotus Resources has completed a A$65 million placement to bolster its uranium projects in Malawi and Botswana, positioning itself for steady production and future expansion.
Maxwell Dee
Maxwell Dee
4 Sept 2025
Lotus Resources has achieved a pivotal milestone by producing its first yellowcake at the Kayelekera Uranium Mine, marking its emergence as a global uranium producer. The company targets ramping up production to 200,000 pounds per month by early 2026.
Maxwell Dee
Maxwell Dee
1 Sept 2025
Lotus Resources has received the final environmental and social approval to restart its Kayelekera Uranium Mine in Malawi, marking a key milestone in its African uranium operations. This endorsement from Malawi’s Environment Protection Authority paves the way for the company’s planned production ramp-up.
Maxwell Dee
Maxwell Dee
5 Aug 2025
Lotus Resources is on track to restart uranium production at its Kayelekera project in Malawi by Q3 2025, backed by binding offtake contracts covering nearly 4 million pounds of uranium and a robust cash position.
Maxwell Dee
Maxwell Dee
31 July 2025
Lotus Resources has initiated processing of high-grade uranium ore at its Kayelekera Project in Malawi, moving closer to first uranium production this quarter. Key infrastructure upgrades, including a new power grid connection, aim to reduce costs and environmental impact.
Maxwell Dee
Maxwell Dee
31 July 2025
Lotus Resources has completed key refurbishments at its Kayelekera Uranium Project in Malawi, restarting the SAG mill and progressing through hot commissioning towards first uranium oxide production this quarter.
Maxwell Dee
Maxwell Dee
14 July 2025
Lotus Resources has begun cold commissioning at its Kayelekera uranium project, targeting a Q3 2025 production restart while adopting an owner-operator mining model to reduce costs and enhance control.
Maxwell Dee
Maxwell Dee
17 June 2025
Lotus Resources has secured Environmental and Social Impact Assessment approval for its Kayelekera Uranium Project in Malawi, paving the way for uranium production to resume in the third quarter of 2025. The company also completed a key board transition, signaling a new phase in its governance.
Maxwell Dee
Maxwell Dee